CompTIA Project+ (PK0-005) Practice Exam
Cover all four Project+ objective areas — project management concepts, life-cycle phases, tools and documentation, and the IT and governance basics — with objective-mapped practice questions, instant feedback in Learn mode, and a full timed simulation in Exam mode. Start with a 24-hour free trial.
Start 24-hour free trial →CompTIA Project+ (PK0-005) exam at a glance
- Vendor
- CompTIA
- Exam code
- PK0-005
- Certification
- CompTIA Project+
- Level
- Entry-level project management
- Blueprint
- Exam version V5, launched November 8, 2022 (current edition)
- Format
- Maximum of 90 questions; multiple-choice and performance-based
- Duration
- 90 minutes
- Passing score
- 710 on a scale of 100–900
- Delivery
- Pearson VUE test center or online proctored
- Recommended experience
- Equivalent to 6–12 months managing projects in a tech environment (recommended, not required)
- Languages
- English, Japanese, Thai
- Renewal
- Valid three years; renew through CompTIA continuing education
Source: CompTIA — Project+ certification (exam details & V5 objectives). Verify current details with CompTIA before scheduling.
About the CompTIA Project+ (PK0-005) certification
CompTIA Project+ is the vendor-neutral credential for managing small to medium-sized projects, especially in a technology setting. It is deliberately broader and lighter than the PMP: where PMI’s flagship targets seasoned project managers and carries strict eligibility requirements, Project+ is built for the working professional who runs projects as part of a wider role — coordinators, team leads, analysts, and accidental project managers — and has no formal prerequisites. It covers both predictive (waterfall) and agile approaches without locking you into a single methodology.
The current exam is version V5 (series code PK0-005), launched in November 2022. It delivers up to 90 questions — multiple-choice and performance-based — across four objective areas, and the weighting is front-loaded on fundamentals: Project management concepts (33%) and Project life-cycle phases (30%) together make up nearly two-thirds of the exam. The remainder covers project tools and documentation, plus a distinctive Basics of IT and governance area that sets Project+ apart from general PM certs. Every PowerKram practice question maps to one of the four areas, so a weak score points you at the exact objective to revisit. For context on the certification-versus-degree decision many candidates weigh, see our guide to choosing certifications over a college degree.
Project+ (PK0-005) exam objectives and weights
CompTIA splits the V5 exam across four objective areas. The weights below are CompTIA’s own and sum to 100% — plan your study time roughly in proportion to them.
Project characteristics and methodologies, agile vs. waterfall selection, change control, risk and issue management, schedule and quality management, communication and meeting management, team and resource management, and procurement.
Discovery artifacts and business cases; initiation (charters, stakeholders, RAMs, kickoffs); planning (scope, schedule, risk, communication); execution (tasks, vendors, budgets, conflict, phase gates); and closing (validation, contract close, lessons learned).
Project tools such as Gantt, burndown, and PERT charts, issue and change logs, risk registers, and dashboards; productivity and collaboration tools; and quality charts including histograms, Pareto, fishbone, and decision trees.
Environmental, social, and governance (ESG) impacts; information security and compliance/privacy; core IT concepts including cloud and software basics; and IT change control such as CI/CD and production vs. staging environments.
Who the Project+ exam is for
Project+ is built for people who manage projects without necessarily being full-time project managers: team leads and coordinators, business and IT analysts, and the “accidental project manager” who has picked up delivery responsibility alongside another role. Because it has no formal eligibility requirements — CompTIA suggests just 6–12 months of hands-on project experience as a guideline — it is a far more accessible first step than PMI’s PMP, while still proving real command of methodology, life cycle, and tools.
If you are mapping out where a project-management credential like this can take you, the Project Manager role guide in our career hub lays out the day-to-day work, the salary range, and the certifications that build on Project+.
What this Project+ practice exam delivers
Score by objective area
Every question is tagged to one of the four V5 areas, so your report shows whether Concepts or Life-cycle phases — the two heaviest — is dragging your score, not just an overall percentage.
Learn mode
Immediate feedback after each question with a full explanation of why the right answer is right and why the others are wrong — built for the judgment-based, “best next action” reasoning Project+ tests.
Exam mode
A timed, 90-question-style simulation that mirrors the 90-minute format and its mix of multiple-choice and performance-based questions, so test day feels familiar.
No setup, no download
Runs in the browser with nothing to install. Your 24-hour trial unlocks the full bank and both modes — no credit card required.
Sample Project+ practice questions
Ten free questions spanning the four objective areas, each with a full explanation. The complete bank is available with the 24-hour trial.
A project team is missing deadlines because roles and responsibilities are unclear. What is the project manager’s best course of action?
- Clarify and communicate roles to all team members
- Increase the project budget
- Shorten the timeline
- Eliminate all meetings
Show answer & explanation
Correct: A — clarify and communicate roles. Unclear responsibilities are the stated root cause, so defining them — often via a responsibility assignment matrix (RAM/RACI) — and communicating them directly addresses the problem and restores accountability.
Why not the others: more budget (B) or a shorter timeline (C) does not resolve role confusion; eliminating meetings (D) removes a coordination channel and would likely make things worse.
Source: CompTIA Project+ objectives — Team & resource management →Midway through execution, the client introduces unexpected scope changes. What should the project manager do first?
- Evaluate the impact and update the project plan
- Ignore the changes
- Add all the changes immediately
- Reassign all team members
Show answer & explanation
Correct: A — evaluate impact, then update the plan. Any scope change must be assessed for its effect on schedule, cost, quality, and risk before it is accepted, then folded into the plan through change control. Assessment comes first.
Why not the others: ignoring the changes (B) abandons the client’s need; implementing them immediately (C) bypasses impact analysis and breaks the baseline; reassigning everyone (D) reacts before the impact is even known.
Source: CompTIA Project+ objectives — Project execution → Further reading: PowerKram — project-management study guides →A team member identifies risks that could delay a deliverable. What is the project manager’s immediate next step?
- Document and assess the risks in the risk register
- Delay the project
- Remove the team member
- Skip risk analysis
Show answer & explanation
Correct: A — record and assess in the risk register. Newly identified risks are logged in the risk register and evaluated for probability and impact so a response can be planned. Formal capture is the disciplined first move.
Why not the others: delaying the project (B) reacts before the risk is even understood; removing the team member (C) punishes good risk identification; skipping analysis (D) ignores a known threat.
Source: CompTIA Project+ objectives — Risk management →Stakeholders want regular updates on project progress. Which tool best facilitates this?
- A project status report
- The risk register
- The change control log
- The issue escalation matrix
Show answer & explanation
Correct: A — a project status report. Status reports are the standard vehicle for communicating overall progress, milestones, and health to stakeholders on a regular cadence.
Why not the others: the risk register (B) tracks risks, the change control log (C) tracks change requests, and the escalation matrix (D) defines who handles escalated issues — each is narrower than a general progress update.
Source: CompTIA Project+ objectives — Project tools → Further reading: PowerKram — business analyst guide →A critical vendor cannot deliver materials on time, threatening the schedule. What should the project manager do?
- Communicate with the vendor and update the schedule as needed
- Ignore the issue
- Replace the entire project team
- Increase meeting frequency
Show answer & explanation
Correct: A — engage the vendor and adjust the schedule. A vendor delay is managed through direct communication to understand the new timeline, then updating the schedule and stakeholders accordingly — addressing the constraint at its source.
Why not the others: ignoring it (B) lets the slip cascade; replacing the team (C) targets the wrong party; more meetings (D) adds overhead without resolving the supply problem.
Source: CompTIA Project+ objectives — Procurement & vendor management →A project is under budget but missing key deliverables. What should the project manager focus on?
- Meeting project objectives and quality standards
- Spending the remaining budget
- Hiring more staff regardless of need
- Changing the project scope
Show answer & explanation
Correct: A — objectives and quality. Success is defined by delivering the agreed scope to the required quality, not by how much budget was consumed. Missed deliverables are the real problem to solve.
Why not the others: spending down the budget (B) is waste, not value; hiring without a defined need (C) may not address the gap; changing scope (D) without analysis can mask the missed objectives rather than fix them.
Source: CompTIA Project+ objectives — Quality & performance management → Further reading: PowerKram — project-management study guides →A team member is struggling with assigned tasks because they lack the necessary training. What is the most effective action?
- Provide the necessary training or resources
- Replace the team member
- Ignore the issue
- Eliminate all meetings
Show answer & explanation
Correct: A — provide training or resources. A skills gap is closed by developing the team member, which addresses the root cause and retains institutional knowledge — the resource-management response Project+ expects.
Why not the others: replacing the member (B) is costly and skips the fixable cause; ignoring it (C) leaves the gap; eliminating meetings (D) is unrelated to a training need.
Source: CompTIA Project+ objectives — Team & resource management →A client requests a change that will raise costs and extend the timeline. What should be done before proceeding?
- Follow the change control process and obtain formal approval
- Implement the change immediately
- Reject all client requests outright
- Shorten the timeline elsewhere to compensate
Show answer & explanation
Correct: A — route it through change control for formal approval. A change affecting cost and schedule must go through the documented change-control process — impact assessment, then a decision from the change control board or sponsor — before any work begins. Authorization protects the baseline.
Why not the others: implementing immediately (B) skips approval and breaks the baseline; rejecting all requests (C) ignores legitimate change; compressing the schedule elsewhere (D) commits to the change before it is even approved and risks new problems.
Source: CompTIA Project+ objectives — Change control → Further reading: PowerKram — project-management study guides →The project team is in conflict over competing priorities. What should the project manager do?
- Facilitate a discussion to resolve the conflict collaboratively
- Assign all tasks to one person
- Ignore the conflict
- Delay the project
Show answer & explanation
Correct: A — facilitate a collaborative resolution. Bringing the parties together to surface priorities and reach consensus is the constructive conflict-management approach, preserving the team and the work.
Why not the others: dumping all tasks on one person (B) creates a bottleneck and resentment; ignoring the conflict (C) lets it fester; delaying the project (D) avoids the issue rather than resolving it.
Source: CompTIA Project+ objectives — Team management & conflict →A project is complete, but the client is dissatisfied with the final deliverable. What should the project manager do next?
- Conduct a lessons-learned review and address the client’s feedback
- Close the project without further action
- Blame the team
- Increase the budget retroactively
Show answer & explanation
Correct: A — lessons learned plus address the feedback. Proper closing captures lessons learned and resolves outstanding client concerns, both improving the relationship and feeding future projects — the disciplined closeout Project+ expects.
Why not the others: closing without action (B) leaves a dissatisfied client and no learning; blaming the team (C) is unproductive and inaccurate; adding budget after completion (D) does not fix the deliverable.
Source: CompTIA Project+ objectives — Project closing →Keep going: study guides and career paths
Project+ proves you can run a project end to end — it pays off fastest when you pair it with the next skill and a clear sense of where it leads. Two PowerKram hubs back this exam up.
Deep dive: Project+ exam structure, scoring, study path & how it compares to the PMP
Exam structure and how it’s scored
The V5 Project+ exam (PK0-005) delivers a maximum of 90 questions in 90 minutes, mixing multiple-choice with a small number of performance-based items. Scoring is scaled from 100 to 900, and the passing mark is 710. Questions are scenario-driven rather than definition-driven — expect to choose the “best next action” from several plausible options, where the wrong answers fail for specific, learnable reasons. See our project-management study guides →
Where the weight sits
Two areas dominate: Project management concepts (33%) and Project life-cycle phases (30%) together make up 63% of the exam. Tools and documentation (19%) and the distinctive Basics of IT and governance (18%) split the rest. That last area — ESG, information security, cloud and software basics, CI/CD — is what sets Project+ apart from a pure PM credential and reflects its tech-project focus. PowerKram’s objective-level scoring surfaces which of the four is dragging your readiness in your first practice run. Read the business analyst guide →
Realistic study path
Project+ assumes only light experience — CompTIA suggests 6–12 months — so most candidates need four to eight weeks: work the four areas, drill objective-tagged practice questions, and re-weight each week toward your weakest area, usually the IT-and-governance basics for non-technical candidates or the formal documentation for hands-on ones. Because the exam rewards judgment over memorization, practising scenario questions and reading the reasoning behind each answer matters more than rote review. Read certifications vs. a college degree →
Project+ vs. the PMP
The two credentials sit at different points on the project-management ladder. Project+ is entry-level and vendor-neutral, with no formal eligibility requirements and a tech-project emphasis — ideal for proving capability early or for professionals who manage projects part-time. PMI’s PMP is the advanced, globally recognized standard, with strict experience and education prerequisites and a deeper, three-domain exam. Many people earn Project+ first and target the PMP once they have the required hours. If you are weighing the step up, our PMP practice exam covers that next tier. Project Manager role guide →
Recommended experience, cost, and delivery
CompTIA recommends the equivalent of 6–12 months managing projects in a tech environment, but there is no formal prerequisite. The exam is delivered through Pearson VUE at a test center or online with a proctor; the online option needs a quiet, private room and a webcam system check. It is offered in English, Japanese, and Thai. Fees and renewal rules vary by region and change over time, so confirm the current voucher price and continuing-education requirements on CompTIA’s site before you book. CompTIA’s official Project+ page →
Start your free 24-hour Project+ practice trial