PMP (Project Management Professional) Practice Exam
Cover all three PMP domains — People, Process, and Business Environment — with objective-mapped practice questions, immediate feedback in Learn mode, and full timed simulation in Exam mode. Start with a 24-hour free trial.
Start 24-hour free trial →PMP exam at a glance
- Vendor
- Project Management Institute (PMI)
- Exam name
- Project Management Professional (PMP)®
- Blueprint
- PMI Exam Content Outline (2021 refresh); verify edition before publish
- Format
- 180 questions (multiple choice, multiple response, matching, hotspot, limited fill-in-the-blank)
- Duration
- 230 minutes (with two optional 10-minute breaks)
- Delivery
- Pearson VUE test center or online proctored
- Passing standard
- PMI does not publish a fixed passing score; results are reported by domain as Above Target / Target / Below Target / Needs Improvement
- Prerequisites
- Secondary degree + 60 months leading projects + 35 hours of project-management education or a CAPM® certification (OR four-year degree + 36 months experience + 35 hours of education or CAPM®)
- Validity
- 3 years; renew with 60 PDUs
Source: PMI — PMP Certification Handbook & Exam Content Outline. Verify current details with PMI before scheduling.
About the PMP (Project Management Professional) certification
The PMP is PMI’s flagship credential for experienced project managers. Since the 2021 exam refresh it covers predictive, agile, and hybrid approaches in roughly equal weight, reflecting how modern project work actually happens — Waterfall-only candidates will find half the exam unfamiliar. Questions are scenario-driven rather than definition-driven; expect to choose “the best next action” from four plausible options, where the wrong answers are wrong for specific, learnable reasons. For foundational reading on the delivery approaches the PMP tests, see the Program Management Fundamentals guide.
PowerKram’s PMP practice exam mirrors that scenario format and maps every question to one of the three official domains (see breakdown below), so your score report tells you which domain to study, not just “more practice needed.”
PMP exam domains and weights
The current PMP exam (2021 refresh, in effect through the next ECO update) splits questions across three domains. Roughly half the exam — 50% — is on Process, but People at 42% is what most candidates underestimate.
Leading, managing conflict, supporting team performance, empowering team members, mentoring stakeholders, and emotional-intelligence skills used to lead through influence.
Project lifecycle execution: scope, schedule, budget, quality, risk, procurement, integration, and the planning – executing – monitoring – controlling work itself, across predictive, agile, and hybrid approaches.
Compliance, project benefits and value, external business environment, organizational change, and how the project connects to broader strategy.
Approximately 50% of questions reflect predictive approaches; the other 50% reflect agile or hybrid. Source: PMI PMP Examination Content Outline.
Who the PMP is for
PMI positions the PMP for practitioners who already lead projects — it is not an entry-level certification. The eligibility rules formalize that: you need either 36 or 60 months of project leadership experience (depending on your degree) plus 35 hours of project-management education before you can sit the exam.
- Project managers and senior project managers formalizing a track record they already have.
- Program and portfolio managers establishing a foundation for further PMI credentials (PgMP, PfMP).
- Scrum Masters, agile coaches, and delivery leads who want a credential that recognises agile and hybrid practice, not only predictive.
- Consultants and PMO leaders whose clients require PMP-credentialed staff on engagements.
If you have less than three years of project leadership, the CAPM is the appropriate first credential and counts toward PMP eligibility. For role-by-role salary ranges and career paths the PMP unlocks, see the Career Hub — Project Manager role guide.
What this PMP practice exam delivers
Learn mode
Get the correct answer, the explanation, and why the other choices were wrong — immediately after each question. Best for the People domain, where the “best next action” is rarely obvious.
Exam mode
180 questions, 230-minute timer, two optional breaks — the real PMP format. Build the pacing and stamina the actual test requires.
Source-linked explanations
Every answer cites the PMI source it derives from (PMBOK Guide, Agile Practice Guide, or Exam Content Outline) so you can verify and dig deeper.
Score by PMP domain
Your results break down by People, Process, and Business Environment — matching how PMI itself reports your real exam result, so practice tells you exactly where to study.
Sample PMP practice questions
Ten free questions, one per domain area, with full explanations. The complete bank is available with the 24-hour trial.
A project manager is initiating a new project. Which document formally authorizes the project to proceed?
- Project charter
- Scope statement
- Risk register
- Work breakdown structure (WBS)
Show answer & explanation
Correct: A — Project charter. The charter is the document signed by the sponsor that formally authorizes the project’s existence and gives the project manager authority to apply organizational resources. Without it, the project is not officially sanctioned.
Why not the others: the scope statement (B) defines deliverables but comes after authorization; the risk register (C) tracks risks and is built during planning; the WBS (D) decomposes scope into work packages and is also a planning artifact. All three are downstream of the charter.
Source: PMI Exam Content Outline — Process domain → Further reading: PowerKram — Project Charter & Authorization →A team is unclear about what is and is not included in the project. Which document provides the clearest authoritative reference?
- Project scope statement
- Issue log
- Communication plan
- Test plan
Show answer & explanation
Correct: A — Project scope statement. The scope statement defines product scope, project scope, deliverables, acceptance criteria, exclusions, assumptions, and constraints — exactly the “what is and is not included” reference the team needs.
Why not the others: the issue log (B) tracks problems already raised, not scope; the communication plan (C) defines who gets what information, not what the project will deliver; a test plan (D) is a quality artifact and only addresses verification, not scope definition.
Source: PMI Exam Content Outline — Process domain (scope) →A stakeholder requests a significant scope change mid-project. What should the project manager do first?
- Evaluate the change’s impact and submit it through the change-control process
- Implement the change immediately to maintain stakeholder relations
- Reject the request because the baseline is approved
- Escalate the request to the sponsor without analysis
Show answer & explanation
Correct: A — Evaluate impact and submit through change control. Integrated change control requires that any change to a baseline be assessed for cost, schedule, scope, quality, risk, and resource impact before approval. The PM’s first move is always evaluation.
Why not the others: implementing immediately (B) bypasses the change-control board and violates baseline integrity; rejecting without review (C) ignores the legitimate possibility that the change adds value; escalating without analysis (D) hands the sponsor a decision they can’t make without the impact data.
Source: PMI Exam Content Outline — Integrated change control → Further reading: PowerKram — Integrated Change Control →A project is reported as behind schedule and over budget. Which technique best diagnoses both dimensions together?
- Earned value analysis (EVA)
- SWOT analysis
- Monte Carlo simulation
- MoSCoW prioritization
Show answer & explanation
Correct: A — Earned value analysis. EVA integrates scope, schedule, and cost into a single set of metrics (SV, CV, SPI, CPI), and is specifically designed to diagnose schedule and budget variance together rather than separately.
Why not the others: SWOT (B) is a strategic-context tool, not a performance diagnostic; Monte Carlo (C) is a risk-simulation technique for forecasting uncertainty, useful for predicting variance but not diagnosing it; MoSCoW (D) is a requirements-prioritization technique with no schedule or cost dimension.
Source: PMI PMBOK® Guide — Earned value analysis →An agile team has just finished an iteration. Which ceremony specifically promotes continuous team improvement?
- Sprint retrospective
- Sprint planning
- Daily standup
- Sprint review
Show answer & explanation
Correct: A — Sprint retrospective. The retrospective is explicitly dedicated to inspecting how the team worked and identifying improvements for the next iteration. It is the only Scrum ceremony whose purpose is the team’s own process improvement.
Why not the others: sprint planning (B) commits to the next iteration’s work; the daily standup (C) synchronises within an iteration; the sprint review (D) inspects the product increment with stakeholders, not the team’s process.
Source: PMI Agile Practice Guide — Retrospectives → Further reading: PowerKram — Agile Ceremonies & Retrospectives →A project manager wants to plan effective stakeholder engagement throughout the project lifecycle. Which document supports this?
- Stakeholder engagement plan
- Risk probability and impact matrix
- Test plan
- Work breakdown structure
Show answer & explanation
Correct: A — Stakeholder engagement plan. This plan defines the strategies and actions required to promote productive involvement of stakeholders. It identifies engagement levels (unaware, resistant, neutral, supportive, leading) and the actions needed to move stakeholders toward their target level.
Why not the others: the risk matrix (B) classifies risks, not stakeholders; the test plan (C) is a quality artifact; the WBS (D) decomposes deliverables, not relationships.
Source: PMI Exam Content Outline — People domain (stakeholders) → Further reading: PowerKram — Stakeholder Engagement →A project will engage multiple external vendors. Which document formally governs each vendor relationship?
- Contract / agreement
- Project charter
- Scope baseline
- Work breakdown structure
Show answer & explanation
Correct: A — Contract / agreement. The contract defines the legally binding terms, deliverables, payments, and remedies between the buyer and seller. It is the authoritative governance document for each procurement.
Why not the others: the charter (B) authorizes the project internally, not the vendor relationship; the scope baseline (C) defines what the project will deliver, not vendor obligations; the WBS (D) decomposes work but has no contractual standing.
Source: PMI Exam Content Outline — Business Environment domain →A team is monitoring process variability over time to determine whether a manufacturing process remains within acceptable limits. Which tool supports this?
- Control chart
- Gantt chart
- RACI matrix
- PERT chart
Show answer & explanation
Correct: A — Control chart. A control chart plots a process variable over time against statistically derived upper and lower control limits, used to determine whether a process is in control (predictable) or out of control (variation requires investigation).
Why not the others: a Gantt chart (B) shows schedule, not quality; a RACI matrix (C) clarifies roles and responsibilities; a PERT chart (D) shows schedule network dependencies and probabilistic duration estimates — none of these address process variability.
Source: PMI PMBOK® Guide — Quality control tools →A project manager wants to eliminate the cause of a high-impact threat entirely rather than mitigate it. Which risk response strategy fits?
- Avoid
- Accept
- Transfer
- Mitigate
Show answer & explanation
Correct: A — Avoid. Avoidance changes the project plan to eliminate the threat or its cause entirely (e.g., changing scope, schedule, or approach so the risk no longer applies).
Why not the others: Accept (B) takes no action and absorbs the consequence if it occurs; Transfer (C) shifts the impact to a third party (insurance, contracts) but doesn’t eliminate the threat; Mitigate (D) reduces probability or impact but the threat still exists.
Source: PMI PMBOK® Guide — Risk response strategies → Further reading: PowerKram — Risk Response Strategies →A project is closing. Which activity best ensures that knowledge gained transfers to future projects?
- Documenting lessons learned and updating the organizational process assets
- Verifying scope with the sponsor
- Performing a final risk reassessment
- Reassigning team members to new projects
Show answer & explanation
Correct: A — Lessons learned documentation, fed back into OPAs. Capturing and storing lessons learned is the specific mechanism by which one project’s knowledge becomes the organization’s asset. Without that step, knowledge leaves with the team.
Why not the others: scope verification (B) confirms deliverables but is not knowledge transfer; risk reassessment (C) is an ongoing planning activity, not a closing one; reassigning the team (D) is administrative and actively works against retention if lessons aren’t captured first.
Source: PMI Exam Content Outline — Closing the project →Keep going: Learning & Career resources
The PMP isn’t a destination on its own — it earns its return when paired with the underlying delivery skills and a clear sense of where it leads. Two PowerKram hubs back this exam up.
Deep dive: PMP exam structure, scoring, study path & recertification
Exam structure and how it’s scored
The PMP delivers 180 questions in 230 minutes, with two optional 10-minute breaks. Question formats include traditional multiple choice (one right answer), multiple response (select two or three), matching, hotspot, and a small number of limited fill-in-the-blank. PMI does not publish a fixed passing score; instead, your result is reported per domain as Above Target, Target, Below Target, or Needs Improvement. Reaching Target or above across all three domains is the practical pass condition. Read the PMP scoring deep dive →
Predictive, agile, and hybrid coverage
Since the 2021 refresh, roughly half the exam reflects predictive approaches and the other half reflects agile or hybrid. In practice that means you cannot pass with PMBOK alone — PMI’s Agile Practice Guide covers the agile content explicitly, and a candidate from a pure-Waterfall background will find a meaningful fraction of the People-domain questions unfamiliar. Conversely, agile practitioners often underestimate the Process-domain depth around earned value, procurement, and risk quantification. Read predictive vs. agile vs. hybrid →
Realistic study path
A typical preparation runs eight to twelve weeks of consistent study: PMBOK Guide and Agile Practice Guide as primary references, scenario-based practice questions weekly, and at least one full timed simulation in the final week. Candidates with strong agile experience often need extra Process-domain work; candidates from predictive PMOs typically need extra People-domain and agile-ceremony work. PowerKram’s domain-level scoring is built to surface that asymmetry early, so weeks 3-6 can be re-weighted toward the weaker domain. Read the 8-week PMP study plan →
Cost, scheduling, and retake policy
PMI membership reduces the exam fee meaningfully and pays for itself if you sit the exam once. The credential is delivered through Pearson VUE at a test center or online with a proctor; the online option requires a quiet, private room and a webcam check. PMI allows up to three attempts within one eligibility year; further attempts require waiting out the year. Verify current fees and policies on PMI’s site before scheduling. PMI’s official PMP page →
Recertification (PDUs)
The PMP is valid for three years. To renew, you earn 60 Professional Development Units (PDUs) in a structured Continuing Certification Requirements (CCR) cycle covering technical, leadership, and strategic/business categories. Many ongoing PMO and consulting roles produce most of these naturally; volunteering, writing, and teaching can supplement. PMI’s CCR Handbook is the authoritative reference. Read the PDU earning guide →
Career outlook for PMP-credentialed practitioners
The PMP remains one of the most-requested project-management credentials in employer postings, particularly in IT, construction, healthcare, and financial services. Compensation impact varies by region and role, but the credential is most economically valuable when paired with a specific domain (e.g., PMP + agile coaching, PMP + PMO leadership, PMP + program management). For salary ranges and role-specific paths, see the Career Hub. Career Hub — Project Management →